Quantcast
Channel: Submarine & Other Matters
Viewing all articles
Browse latest Browse all 2347

Oyashio - Soryu Table, Aus Future Submarine Program, ¥ in, Dragons out

$
0
0
OYASHIO - SORYU TABLE (latest as at January 17, 2016)

SS

No.
Building

No.
Pennant

No.
MoF approved amount ¥ Billions) & FY*
LAB, LIB, AIP **
Laid Down
Laun

-ched
Commi-ssioned
Built

By
5SS

8105
SS-590/ TS3608
¥52.2B

FY1993
LAB only
 Jan 1994
Oct 1996
March 1998
 KHI
6SS-
15SS


10 subs
8106

-8115
SS-591

-600
¥52.2B

Per sub

FY1994

-FY2004
LAB only
 Feb 1994
March 2008
 MHI

&

KHI
16SS SoryuMark 1
8116
SS-501
¥60B

FY2004
LAB + AIP
March 2005
Dec 2007
March

2009
MHI
17SS
8117
SS-502
¥58.7B
LAB + AIP
March 2006
Oct 2008
March

2010
KHI
18SS
8118
SS-503
¥56.2
LAB + AIP
Feb 2007
Oct 2009
March

2011
MHI
19SS
8119
SS-504
¥53BFY2009
LAB + AIP
March 2008
Nov 2010
March

2012
KHI
20SS
8120
SS-505
¥51B
LAB + AIP
March 2009
Oct 2011
March

2013
MHI
21SS
8121
SS-506
 ?
LAB + AIP
January 2011
Oct 2013
March

2015
KHI
22SS
8122
SS-507
¥52.8B
LAB + AIP
Feb 2012
Oct 2014
March

2016?
MHI
23SS
8123
SS-508
¥54.6B
LAB + AIP
March
2013
Nov2 2015
2017?
KHI
24SS
8124
SS-509
¥54.7B
LAB + AIP
2014
2016?
2018?
MHI
25SS
8125
SS-510
¥53.1B
LAB + AIP
2015
2017?
2019?
KHI
26SS
8126
SS-511
¥51.7B
LAB + AIP
2016?
2018?
2020?
MHI
27SS

Soryu

Mark 2
8127
SS-512
¥64.3B
LIB only
2017?
2019?
2021?
KHI
28SS
8128
SS-513
¥63.6B
LIB only
2018?
2020?
2022?
MHI
29SS
8129
SS-514
  ?
LIB only
2019?
2021?
2023?
KHI
Aus1

***
 Super Soryu Australia
LIB only
2023?
2025?
2027?
Kobe?
Aus2 to 6?
 Super Soryu Australia
LIB only
2024?
2026
2028
in Aus?

Table mainly courtesy of updates provided to Submarine Matters by Japanese sources. Note that it summarises the 11 submarines of the Oyashio Program (5SS - 15SS) then continues through the Soryu Program (16SS onwards)

* The Dragon names have been removed – while important in Japanese culture such names are not important to Australian or Americans. Instead the column is filled with Japanese Ministry of Finance (MoF) approved Budget Amounts in Yen (¥) Billions (B) (¥1 Billion = A$12 million on Jan 15, 2016). FY = First Year of Budgeting. These Yen  and FY years were provided by S to Submarine Matters for the article of January 13, 2016.

** LAB = lead-acid batteries, AIP = air independent propulsion, LIB = lithium-ion batteries. 


On January 16, 2016 in the Comment Thread S explained:

“The budgets for the Soryu are 20SS (¥51B), 22SS (¥52.8B), 23SS (¥54.6B), 24SS (¥54.7B), 25SS (¥53.1B) and 26SS (¥51.7B). [I found a gap in the Table, 21SS was missing, now fixed. S do you have the ¥B figure for 21SS?] The fluctuation of the cost is due to a combination of yearly small modifications and a continuous effort toward cost reduction as follows:

-  the MoD investigates the flow of funds to private companies on payee, expenditure and contract for procurement of submarines, and confirms that there are no problems. The cost audit after fulfillment of submarine building has been conducted from FY2002.

-  as a result of effort toward cost reduction including use of government supply, adoption of open tender and reduction of man-hours, the executed price has gradually decreased from FY2004 to FY 2007.

The man-hours of the second batch of MHI and KHI launched submarines (18SS and 19SS respectively) is about 10% lower than for the first batch (that being MHI 16SS and KHI 17SS) achieved by reduction of man-hours. This is achieved through learning, setting of standard man-hours for similar work and through time management.

PETE COMMENT 

The broad future decisions on the Australian choice (of Japan, TKMS or DCNS) are up to the National Security Committee of the Australian Cabinet with a decision likely late 2016. Much will then depend on a managerial-industrial mix of Australian companies and the "winner" (eg. Japan) building 2/3s of the subs and US companies (Raytheon and/or Lockheed Martin (as possible integrator) for 1/3 = Combat System and Weapons). Ideally Japanese expertise/experience will have main carriage of the 2/3s + 1/3s integration as a it would be messy if all three countries were constantly negotiating throughout the Program.

Undelining that the Submarine Program would not be just an Australian-Japan affair is that politically powerful Lockheed Martin has opened a Combat System Laboratory in Adelaide. A US citizen (Rear Adm (rtd) Stephen Johnson US Navy) has already been appointed General Manager, Australian Future Submarine Program - presumably he is well placed to manage and balance US, Japanese and Australian interests. 

Regarding “Aus1 ***” in the Table the dates and places where the subs are built inevitably involves opinion. Aus1 is the first of class for Australia. It may make sense to have it built in Kobe, Japan to ease initial construction, testing and certification issues. From Aus2 the numbers only go up to Aus6 in the Table because only 6 subs might be built (based on the formula 6 + 2 (maybes) used for the Oberons and Collins). Building Aus2 to Aus6 in Kobe need only be a last resort if a re-run of the Collins or Air Warfare Destroyer (see 2010 onwards) problems are developing. Such a things-going-wrong situation obviously needs to be picked up early (eg. in 2023).

Whatever happens, if Japan is chosen, the materials for the submarines will mainly be produced in Japan (mainly by MHI and KHI?) and the Combat System in the US.

As with other Japanese ventures in Australia (eg. car factories) a large number of Japanese managerial and technical advisers should be in Australia. 

The clear record of Japanese submarine building discipline should produce a positive industrial and political (Federal and State levels) experience, thus minimising anarchy.

A useful and basically new background reference on the Future Submarine (Collins Replacement) Program is here.

Pete

Viewing all articles
Browse latest Browse all 2347

Trending Articles